What is the installation process of Pressurised Dissolved Air Flotation equipment

2025-09-06

Pressurised DAF Equipment Installation Guide

Proper installation is crucial for optimal performance of Dissolved Air Flotation systems

Pre-Installation Preparation Phase 1

The installation begins with thorough pre-installation preparation to ensure the site meets all requirements.

  • Evaluate the installation site for flatness and stability
  • Ensure sufficient space for access and future maintenance
  • Verify clear pathways for pipelines and electrical systems
  • Inspect all equipment parts for damage or missing items
  • Confirm components match manufacturer's specifications

An uneven surface can cause instability in the DAF tank and affect operational performance.

Core Components Installation Phase 2

The second step involves installing the core components of the DAF system.

DAF Tank
Pressure Vessel
Air Compressor
1

DAF Tank Installation

Position the tank on a flat surface and secure it to prevent shifting. Use anchor bolts or stabilizing pads depending on size and weight.

2

Pressure Vessel Mounting

Mount in a location that allows easy connection to both the air compressor and the DAF tank.

3

Air Compressor Placement

Place in a well-ventilated area to ensure proper heat dissipation, with attention to reducing vibration.

Alignment is critical: Misalignment can disrupt water flow and bubble distribution.

System Connections & Debugging Phase 3

The third phase focuses on system connections and initial debugging.

1

Pipeline Connections

Connect pipelines between the DAF tank, pressure vessel, air compressor, and water inlet/outlet points.

2

Electrical Connections

Link the control panel to the compressor, pumps, and sensors. This work should be done by qualified personnel.

3

Preliminary Testing

Conduct a preliminary test: fill the system with water, activate the compressor to check air flow and pressure levels.

Seal integrity: All pipe joints must be sealed tightly to prevent leaks that can reduce pressure and compromise air dissolution.

Inspection & Acceptance Test Phase 4

The final step is a comprehensive inspection and acceptance test.

  • Operate the entire system at normal conditions to evaluate performance
  • Check for leaks in pipelines and joints
  • Verify that bubbles form uniformly in the DAF tank
  • Confirm control panel accurately monitors and adjusts parameters
  • Review operation manuals with on-site staff

Once all checks pass and the system operates as expected, the installation process is considered complete.